Lead Time Calculator: Working Days and Delivery Date

Lead time calculator

Calculate a completion or delivery date, work backward from a required date, or measure actual lead time. Break the total into supplier, production, inspection, transit and safety-buffer days, with calendar or working-day rules.

Comma-separated ISO dates. Applied only to working-day calendars.
Completion date
Counted lead time
Calendar span
Excluded dates


Lead-time formulas

total planned lead time = supplier + production + inspection/packing + transit + safety buffer

Forward planning advances from the start date until the selected number of eligible days has been counted. Reverse planning moves backward from the required date by the same rule. Measuring counts eligible dates after the start through the end; selecting the inclusion option also counts the start date when eligible.

A calendar-day schedule treats every date as eligible. Monday–Friday and Monday–Saturday schedules skip their non-working weekdays and any valid custom excluded dates. A holiday falling on an already excluded weekday is removed only once.

Checked examples

ScenarioInputsExpected result
Simple calendar planSeptember 21, 2026 + 12 calendar daysOctober 3, 2026 when the start date is excluded
Monday–Friday planFriday, September 18 + 1 working dayMonday, September 21
Included startMonday + 1 working day, count startThe same Monday
Custom exclusionMonday + 2 working days; Tuesday excludedThursday
Reverse planningRequired Monday; 1 Monday–Friday dayPrevious Friday when the required date is excluded
Measure actual lead timeMonday to Friday, start excluded4 working days
Component total3 + 5 + 1 + 2 + 1 days12 counted lead-time days

How to use the calculator

  1. Choose forward planning, reverse planning or measurement.
  2. Select calendar days, Monday–Friday or Monday–Saturday.
  3. For planning, enter whole-day components. For measurement, enter the start and completion dates.
  4. Add organization-specific closure dates if needed.
  5. Decide whether the anchor date should count when eligible.
  6. Calculate and review both counted lead time and elapsed calendar span.
Planning limits: Results follow only the calendar and dates entered. They do not know carrier service levels, supplier capacity, cut-off times, time zones, customs delays, regional holidays, contractual definitions or live shipment status. Confirm the counting convention and closures used by the responsible organization.

Frequently asked questions

What is included in lead time?

This calculator lets you total supplier or queue time, production, inspection or packing, transit and a safety buffer. Rename those components mentally to match your process; the arithmetic is their sum.

Does lead time include weekends?

It depends on the chosen calendar. Calendar days include every day; working-day modes skip Sunday or both Saturday and Sunday.

How are holidays handled?

Enter known closure dates in YYYY-MM-DD format. They are excluded only in working-day modes because all dates are eligible in calendar-day mode.

Is the completion date guaranteed?

No. It is an arithmetic plan from supplied assumptions, not a carrier, supplier or contractual commitment.

What is the difference between lead time and cycle time?

Lead time commonly spans the full wait from request or order to completion. Cycle time commonly focuses on active production. Definitions vary, so align the components with the process being measured.